The project involves local improvements on the railway network, such as Underpasses, Railway Stops and Railway Bridges.
In more detail, the project includes the following:
Project Summary
Total Budget :
35.4 mil. Euros approx.
Payment Sources :
Operational Programme “Transport Infrastructures, Environment and Sustainable Development 2014-2020”
- Railway Stop in Neos Panteleimonas, Pieria
The project involves a new railway stop to be built on the Double-Track High-Speed Railway Line Athens – Thessaloniki in Platamonas area, after the exit of Platamonas Castle tunnel, under the existing footbridge.
Funding:
Operational Programme “Transport Infrastructures, Environment and Sustainable Development 2014-2020”
Project cost:
1,0 mil. Euros approx.
Estimated start of construction: 2019
Estimated project completion: 2020
- Railway Bridge in Gallikos river
The project involves the construction of a new railway bridge at Ch. 9+184 of the Thessaloniki – Florina railway line, which is planned to replace the existing steel bridges.
Funding:
Operational Programme “Transport Infrastructures, Environment and Sustainable Development 2014-2020”
Project cost:
7,3 mil. Euros approx.
Estimated start of construction: 2019
Estimated project completion: 2021
- Construction of Grade-Separated Road Crossing in the area of Veria R.S.
The project involves the construction of a grade-separated crossing near Veria Railway Station, in order to serve vehicles coming from Veria R.S., as well as the restoration of traffic in the areas on either side of the railway line.
Funding:
Operational Programme “Transport Infrastructures, Environment and Sustainable Development 2014-2020”
Project cost:
8 mil. Euros approx.
Estimated start of construction: 2019
Estimated project completion: 2021
- Construction of Grade-Separated Road Crossing in in the area of Gefyra Railway Station
The project involves the construction of a grade-separated crossing near Gefyra Railway Station, in Thessaloniki. It includes the construction of a regional road Overpass, over OSE’s group of lines, and the construction of retaining walls in the access ramps.
Funding:
Operational Programme «Transport Infrastructures, Environment and Sustainable Development 2014-2020»
Project cost:
8 mil. Euros approx.
Estimated start of construction: 2018
Estimated project completion: 2021