Press release
Athens, 23 February 2021
The contract for the construction of the railway station in Neos Panteleimon, Pieria was signed
Another project concerning the modernisation of the country’s railway network is proceeding according to the schedule of ERGOSE. Specifically, yesterday, February 22, the contract for the construction of the Railway Station in Neos Panteleimon of Pieria (T.N. 752) was signed, for a contract price of 801.561,78 Euro (excluding VAT), which is financed from European Union funds through the Cohesion Fund of the Operational Programme “Transport Infrastructure, Environment & Sustainable Development 2014 – 2020”.
The contractor of the project, which was tendered through the platform of the National Electronic Public Procurement System (NEPPS.), was declared the company “SOLIS ANONYMOUS TECHNICAL COMPANY” with the distinctive title “SOLIS S.A.”. The selection of the contractor for the construction of the project was carried out in accordance with the “open procedure” of article 264 of Law No. 4412/2016 and under the conditions defined by this law.
The physical scope of the project concerns the construction of the following:
- two platforms on either side of the existing high-speed railway lines (HSR), each 150 m long and 4 m wide
- a staircase with a lift
- a 30 m long earth retaining wall on the upper side of the HSR dock
- two metal shelters on the platforms, each 35 meters long
In addition to the above, the contractor undertakes the landscaping of the surrounding area on the side roads in the area of the Railway Station, the management and removal of rainwater, the electric lighting of the platforms and surrounding area, the electrical protection of metal structures adjacent to the railway lines due to electrification, as well as the temporary and permanent safety measures for employees and the public.
It is noted that the construction period of the project is 24 months, with an additional 24-month period of mandatory maintenance after completion.
Regarding the signing of the contract, the Managing Director of ERGOSE Mr. Christos Vinis noted: “ERGOSE is proceeding rapidly with the implementation of its mission, the completion of the modernization and expansion projects of the country’s railway network. With continuous project announcements, tenders and contracting, the projects are progressing, while at the same time we are planning new projects that will contribute to the upgrading and completion of the Greek railway system.”
For more information you can contact the following contact details:
Tel: 210 5283 492
Email: info@ergose.gr
About ERGOSE:
ERGOSE S.A. was established in 1996 as a subsidiary of OSE and belongs to the public utilities. The company’s mission is to complete a modern railway network that will constitute an important development pillar for the Greek economy and society, contributing to the safety and speed of transport of people, goods and freight. In this context, ERGOSE S.A. currently manages the modernization projects of the railway lines and facilities of OSE co-financed by the Operational Programmes of the National Strategic Reference Framework (NSRF) 2014-2020 from the Connecting Europe Facility (CEF) 2014-2020 as well as projects with purely national funding that are necessary to complete the investments of the co-financed programmes. The company currently employs more than 200 experienced and highly qualified staff, while it has been providing its services for more than two decades, responding effectively and reliably to the implementation of projects through its excellent organization, structure and systems.