Athens, 6 July 2022
Signing of the contract for the installation of the electrification system on the new double railway line Kiato – Rhododafni
Athens 6 July 2022 – ERGOSE’s planning for the completion of key infrastructures that upgrade the country’s railway network is progressing at a steady pace and according to schedule. The electrification project on the new high-speed railway line connecting Kiato with Rhododafni is on track for implementation.
In particular, today the contract for the project concerning the installation of electrification and anti-noise barriers on the new double railway line Kiato – Rododafni was signed.
The contractor of the project is the consortium TERNA S.A. – Mytilineos S.A. The cost of the project amounts to €84 million (including VAT) and will be implemented over a 30-month period.
The new double railway line is 70.6 kilometres long and with electrification, trains will be able to reach speeds of up to 200 km/h. At the same time, it includes telecommunication systems for passenger information, announcement system, emergency calls and intercom, closed circuit television, planting, installation of anti-noise barriers at localised points.
The project has been co-funded by the European Union, through the NSRF 2014-2020, under the Operational Program “Transport Infrastructure, Environment and Sustainable Development” (OP-Transport Infrastructure, Environment and Sustainable Development).
In summary, the scope of the project concerns:
- Construction of an electrification system and an overhead contact line system with remote control (SCADA) from the traffic control centre.
- Planting of the areas near the substations in accordance with the environmental conditions.
- Installation of anti-noise barriers and noise measurement station system required under the environmental conditions of the project and the applicable Greek and European legislation.
- Installation of passive data and signal transmission network for railway systems.
- Installation of Passenger Information System.
- Installation of Announcement System, Emergency Calls and Intercommunication.
- Installation of Closed Circuit Television System in the Railway Tunnels of the Kiato – Rododafni line section.
- Installation of signage for stops and stations.
The President and CEO of ERGOSE, Mr. Christos Vinis, mentioned, “ERGOSE’s goal is to complete the modernization of the country’s railway network in the shortest possible time, with absolute commitment to the conditions of integrity, quality and safety of transport. Another important project, the installation of an electrification system on the new double line Kiato – Rhododafni, is moving from the design and tendering process to the construction phase.”
For more information you can contact the following contact details:
Tel: 210 5283 492
Email: info@ergose.gr
About ERGOSE:
ERGOSE S.A. was established in 1996 as a subsidiary of OSE and belongs to the public utilities. The company’s mission is to complete a modern railway network that will constitute an important development pillar for the Greek economy and society, contributing to the safety and speed of transport of people, goods and freight. In this context, ERGOSE S.A. currently manages the modernization projects of the railway lines and facilities of OSE co-financed by the Operational Programmes of the National Strategic Reference Framework (NSRF) 2014-2020 from the Connecting Europe Facility (CEF) 2014-2020 as well as projects with purely national funding that are necessary to complete the investments of the co-financed programmes. The company currently employs more than 200 experienced and highly qualified staff, while it has been providing its services for more than two decades, responding effectively and reliably to the implementation of projects through its excellent organization, structure and systems.